What is the fundamental difference between additional and supplementary work?
Construction takes shape not only in plans, but also in legal frameworks. In our INspect-LEX Blog, we explain in plain language the legal concepts and rules that define the world of design and construction.
In the first part of our legal blog series, we highlight the essential difference between supplementary work and additional work.
Distinguishing between additional and extra work in design contract performance
One of the greatest difficulties for designers during design projects is determining when requests arising from the client’s expectations or designs prepared based on the contract between the parties can be considered additional or supplementary work.
Section 6:244 of the Hungarian Civil Code generally provides guidance on the distinction between additional and supplementary work.
Additional work:
The contractor shall also perform tasks that are determined in the contract to produce a work but were not taken into account when the contractor’s fee was set, and also those without which the creation of the work suitable for its designated purpose cannot occur.
The designer is therefore obliged to perform any tasks that were not taken into account when determining the fee, or without which the design is not suitable for subsequent implementation or the property cannot be constructed to meet the client’s expectations, without additional remuneration.
Supplementary work:
The contractor shall also perform tasks that were ordered subsequently, in particular those that became necessary due to the amendment of the design, if their performance does not make the work disproportionately more burdensome.
This is clearly a subsequent requirement on the part of the customer, especially if it necessitates changes to the designs. However, this must not place a disproportionate burden on the designer.
In this regard, legislation establishes multiple conditions for the parties involved. Generally, the designer is obliged to carry out subsequently ordered work, or part of it, and is entitled to an additional design fee for doing so. If this would place an unreasonable burden on the designer, they may reject the client’s request for supplementary work.
In the event of a dispute, experts will decide whether additional or supplementary work was required in a given case. However, a properly structured design contract allows the parties to settle this issue in advance as comprehensively as possible.
Dr. Zsuzsanna Farkas, lawyer
Legal advisor to STUDIO IN-EX integrated design firm
András Szántó, certified architect
Senior architect at STUDIO IN-EX integrated design firm
Recent posts
Model Checking Is Not About Finding Errors
In model-based design, a BIM model is no longer just a 3D representation. A well-structured model contains geometry, information, and discipline-specific relationships in a single source of truth. It drives drawings, quantity take-offs, schedules, equipment lists, technical data deliverables, and serves as the common platform for multidisciplinary coordination.
Innovative Operational Development Based on BIM
We had the opportunity to present at the PropTech Hungary 2026 Conference the operational approach that STUDIO IN-EX has been developing over the past several years. It is a great honour for us that our submission was awarded 2nd place in the Corporate Innovator category.
Challenges in waterproofing design
Our task in this project was to prepare the detailed design documentation for the expansion of a pharmaceutical manufacturing plant. A major technical challenge during the design phase was that the development area is located in the floodplain of the Gyöngyös stream.
Symbiosis at the Design Table: How Mechanical Engineering and Building Automation Merged at STUDIO IN-EX
One of the greatest advantages of a closed BIM based design process is its ability to continuously reveal new opportunities for improvement.
The Art of Accountability at IN-EX: Transforming Control into Motivation
For us, accountability is not a tool of fear, but one of professional security. When tasks are clear (SMART) and feedback is fact-based and constructive (AID), team members know exactly where they stand, where they excel, and where they still need to grow. This is how accountability becomes an internal, supportive driving force.
More than 120 of our employees have earned a Revizto Academy certificate
More than 120 engineers and project coordinators have successfully earned the Revizto Academy Collaboration Core certification.