Blog
Hydro Extrusion’s aluminium recycling plant: the casting pits
We have previously reported on the general outlines of our Hydro aluminium foundry project in Székesfehérvár. By focusing on the designing process and the aspect of civil engineering, now we would like to briefly present the most interesting part of the technology, namely the casting pits.
During the casting process, the molten aluminium is cleaned of dissolved gases and other physical impurities, and the molten metal is then fed through channels to one of two casting stations. During the crystallising process, heat is removed here by cooling water to create the circular aluminium ingots.
This process is served by the two casting pits, which are made up of the following units from bottom to top: between -25 m and -12 m, the hydraulic working cylinder of the casting table is housed in a closed steel tube with a diameter of 1.10 m, which is fixed by concrete lining in an external steel tube with a diameter of 1.80 m. The outer pipe was required to contain the working area and was inserted into a 2.00 m diameter drill hole, followed by 5.00 m of concrete backfill with slurry support to prevent floating and finally the concrete-lined “utility pipe” to contain the working cylinder.
This structure is connected 12 metres below ground level via a 1.65m-thick base plate to the casting pits, in which the casting tables used for casting can move. During the casting process, these are gradually lowered into the cooling water pit and the solidified aluminium billets are then lifted so that they can be lifted out by using a crane. The challenge was also that the temperature of the cooling water can be as high as 60°C, and the whole structure stands 5-7 m above this, while dust dryness requirements were specified for the casting pits. This is to ensure that the process water does not contaminate the environment and that the groundwater cannot contaminate the aluminium. In addition to this, another challenge was the fact that the lifting of the tray can generate a moment of up to 1700 kN/m, which the technology transfers to the base plate through a 2.00 m diameter, 110 mm thick steel disc, which had to be positioned with millimetre tolerances during the iron assembly.
millimetre tolerances during the iron assembly. Due to the complexity of the task, the reinforcement of the base plate and the disc were 3D-reinforced to minimise problems during construction. We also had to coordinate all this with the furnace shafts between the floor line and -4m, and with the mechanical and electrical wiring designed by the technologist, during which 35 watertight breakthroughs were individually designed as detailed as possible, just for the casting pits. The entire process is completed by a cooling basin and a water tower outside, which circulate the water in a closed system, so that only the loss occurring during evaporation needs to be filled up in the process.
In the following posts, we will also present other challenges regarding the supporting structure and the ventilation of the building, which presented us with similar difficulties as the casting pits.
If you have missed our previous article, find it here: Hydro Extrusion’s new aluminium recycling plant
Dániel Dobszai, Dávid Mészáros, Kamilla Zámbó, architects
Recent posts
From idea to impact
At IN-EX, we believe that our greatest asset is the knowledge, experience and curiosity of our people. The Innovation Hub was created to ensure that our engineers’ ideas do not remain isolated suggestions: we give them space, develop them together, and take initiatives that create real value all the way through to implementation.
Structural Challenges of an Automated Warehouse System and a BIM-Based Solution
Our project serves as a good example of how adapting existing industrial buildings to modern technologies can present a complex engineering challenge. The implementation of the automated high-bay warehouse system involved not only a technological conversionbut also the adaptation of an existing reinforced concrete hall structure to new operational, structural, and fire safety requirements.
New Technology, Existing Structure: A Steel Structural Solution for the Conversion of an Automated High-Bay Warehouse
During the interior conversion of a high-bay warehouse attached to a manufacturing plant, it became necessary to install a state-of-the-art automated storage system. In the first phase of the project, we were commissioned to assess, at the conceptual design stage, whether the existing structural framework was suitable for accommodating the new technological system and to determine what structural modifications would be required to implement the conversion.
One Office, One Model: The Benefits of 3D Design and Multidisciplinary Collaboration
STUDIO IN-EX is a multidisciplinary design studio where almost every design discipline is represented under one roof. Every day, our colleagues experience the benefits of having designers from different disciplines work side by side, within a shared closed BIM environment and in the same office. What are these benefits in practice? We spoke to Lilla Vámos, one of our low-voltage systems designers, about her experience.
Case Study: Saving on Investment Costs Through Smart Warehouse Design
We believe that the investment cost of a project can be influenced to a significant extent during the design phase. For this reason, our approach goes beyond simply meeting the applicable requirements. We also investigate alternative technical solutions that can provide the same level of technical performance and safety while resulting in lower investment costs.
Model Checking Is Not About Finding Errors
In model-based design, a BIM model is no longer just a 3D representation. A well-structured model contains geometry, information, and discipline-specific relationships in a single source of truth. It drives drawings, quantity take-offs, schedules, equipment lists, technical data deliverables, and serves as the common platform for multidisciplinary coordination.