Blog

A support structure design challenge: the Danish plastic toy manufacturing and packaging plant

2023.05.18.

We have completed the construction of one of our design projects from 2020. In this post we present one of the four main buildings of the complex, a 9,000m2 packaging plant. The construction of the building started in mid-2021 and was completed in the first quarter of 2023. STUDIO IN-EX was asked to be the general designer for the construction designs and to support the construction of the buildings in the framework of a design engineer’s site supervision.

The fact that all disciplines work in the same space in our office was a great advantage during the design process, as it required constant collaboration between the design studios. Our designers all work on a common platform, a closed-BIM system, which makes their work extremely efficient. Any modifications to the structure were immediately reflected in the model, making them traceable in minutes during the design process. In all cases, the construction designs are submitted to the construction company after several rounds of clash detection in order to minimise construction errors. In addition to the 8,000m2 of packaging technology in the hall area, the main function is served by a 2×1,000sqm two-storey workshop and an office block.

IIt was a real challenge for our structural engineers: The building is a precast reinforced concrete frame structure with pile foundations. The service headquarters was also built with a prefabricated frame slab floor consisting of hollow core slabs. The main vertical load-bearing element of the structure are the 75x75cm columns, which are supported by 120cm high prefabricated pocket necks, which also stiffen the hall in the horizontal direction. The roof structure consists of a series of 150cm high spine purlins with a span of 26.5m-23.8m-26.5m and 165cm high main beams with a span of 18.0m.

The roof structure consists of a series of 150cm high spine purlins with a span of 26.5m-23.8m-26.5m and 165cm high main beams with a span of 18.0m.

On the roof structure, 10.5m above the central section of the hall area, there is a steel-framed mechanical superstructure with a reinforced concrete slab, which houses three 9-ton air handling machines. The roof level with its superstructure and mechanical systems was subjected to significant loads, and we had to cope with the increased stresses from the earthquake during the designing.

Author: Norbert Ábelovszki, Head of the Structural Design Team

Recent posts

2026.09.25.

From idea to impact

At IN-EX, we believe that our greatest asset is the knowledge, experience and curiosity of our people. The Innovation Hub was created to ensure that our engineers’ ideas do not remain isolated suggestions: we give them space, develop them together, and take initiatives that create real value all the way through to implementation.

2026.09.23.

Structural Challenges of an Automated Warehouse System and a BIM-Based Solution

Our project serves as a good example of how adapting existing industrial buildings to modern technologies can present a complex engineering challenge. The implementation of the automated high-bay warehouse system involved not only a technological  conversionbut also the adaptation of an existing reinforced concrete hall structure to new operational, structural, and fire safety requirements. 

2026.09.18.

New Technology, Existing Structure: A Steel Structural Solution for the Conversion of an Automated High-Bay Warehouse 

During the interior conversion of a high-bay warehouse attached to a manufacturing plant, it became necessary to install a state-of-the-art automated storage system. In the first phase of the project, we were commissioned to assess, at the conceptual design stage, whether the existing structural framework was suitable for accommodating the new technological system and to determine what structural modifications would be required to implement the conversion.

2026.09.08.

One Office, One Model: The Benefits of 3D Design and Multidisciplinary Collaboration

STUDIO IN-EX is a multidisciplinary design studio where almost every design discipline is represented under one roof. Every day, our colleagues experience the benefits of having designers from different disciplines work side by side, within a shared closed BIM environment and in the same office. What are these benefits in practice? We spoke to Lilla Vámos, one of our low-voltage systems designers, about her experience.

2026.09.03.

Case Study: Saving on Investment Costs Through Smart Warehouse Design

We believe that the investment cost of a project can be influenced to a significant extent during the design phase.  For this reason, our approach goes beyond simply meeting the applicable requirements. We also investigate alternative technical solutions that can provide the same level of technical performance and safety while resulting in lower investment costs. 

2026.08.05.

Model Checking Is Not About Finding Errors 

In model-based design, a BIM model is no longer just a 3D representation. A well-structured model contains geometry, information, and discipline-specific relationships in a single source of truth. It drives drawings, quantity take-offs, schedules, equipment lists, technical data deliverables, and serves as the common platform for multidisciplinary coordination.